Section 1 & 2 (Dhaka to Mawa) Project Progress Pictures (Dhaka to Mawa) January 2021 Br-40, Ch. 37+300, after erection of 8nos main girder Br-40, erection of 35.0m (43.7ton) 2nos STPG @ span A2~P3 Br-40, synchronized double crane used for erection of 35.0m (43.7t) STPG Bridge #5’s Pile#P179-5, Ch.14+355 concrete pouring is ongoing CMP work at ch.30+000 Cmp work Ch 29+995 CMP work water, cement slurry check (1.74) at ch. 30+000 Compressive strength testing for M35 m50 m40 at Ch 11+500 central lab Concrete slump checked at present of RE sir.Concrete slump 160mm.precast yard div-2,unit-1 at Ch.6+645 Cul-15, Ch. 28+935, preparation ongoing for casting of R.S base slab Drainage layer check at ch 30+330 Excavation is ongoing for 33kV cable laying from ch 7+600 to ch 7+750.. FDD Test Ch 32+517-553 P214 pile cap casting ongoing. Slump Found okay Precast pile rebar cage fabrication checked & found ok Sampling of coarse aggregate at ch 11+500 batching plant 6+000 km Lab on 7.2.21 Ch 11+500 central lab Slump 180 mm of M 40 for Precast Pile at 6+000 km Batching Plant on 07-02-21 Span @P146-P145 , ch. 12+935 Lifting & positioning is on going UP-41 Excavation is ongoing for 33kV cable laying from ch 7+600 to ch 7+750 Project Progress Pictures (Dhaka to Mawa) December 2020 Project Progress Pictures (Dhaka to Mawa) November 2020 Project Progress Pictures (Dhaka to Mawa) October 2020 Ch11+500-Pre-casting of box girder segments Lifting box girder segment onto flat-bed trailer Ch11+500-Box girder segments stock area Ch52+200-Concreting of box girder segment Ch11+369-Drilling construction of trial pile TPA-1 Ch67+424-Steel casing driving for bored working pile Ch67+629-Rebar installation for pile cap A2 Ch42+600-Formwork assembly for construction of pier body Ch22+300-Completed piers Ch22+500-Box girder segments intended for erection Ch22+500-Lifting box girder segments into position Ch22+500-Lifting box girder segments into position P1-20191012-Ch.13+649.419-Borehole Construction P3-20191029-CH22+266.100-Placing Rebar Cage P6-20191208-CH13+315.670-Pile Underwater Concreting P10-20191005-Ch22+104.45-Static Load Test P13-20191009-Ch11+500-Fabrication of Rebar Cage P21-20191123-Ch22+380-Installation of Pile Cap Formwork P23-20191226-Ch22+304-Fabrication of Pier Formwork P24-20191123-Ch.22+342-Pier Cap Concreting P25-20191210-Ch22+304-Box Girder Erection Machine Fabrication P26-20191210-Ch22+304-Box Girder Erection Machine Fabrication P27-20191210-Ch22+304-Box Girder Segment Transportation P28-20191007-CH117+420-Batching Plant Construction P29-20191015-Ch117+420-Temporary Trestle Bridge Construction